Community
Meeting
A community meeting was held on
July 21.
To view the slide
presentation from this meeting,
click here
to view the question and answer
discussion,
click here.
Project
Update
The construction season for 2009
is nearly completed. By the end
of December, construction on
11th St., NW will be finished
for the season. Major
construction activities will be
completed by year’s end, with
some final activities to take
place in spring 2010.
-
Excavation and base course
asphalt for the last section
of roadway on the west side,
between M St. and L St., is
anticipated to be complete
in December. The concrete
safety barriers will be
removed once this final
section is completed.
-
WASA’s 24-inch and 8-inch
waterlines are completed.
-
Parking restrictions have
been lifted throughout the
project area other than in
the construction area
between M. St. and L. St.
-
New signs have been
installed. They will be
uncovered once the section
of roadway between M St. and
L St. is completed.
-
Streetlight poles have been
installed throughout the
project area. The
streetlights between M St.
and O St will be operational
by the end of December.
Streetlights between L St.
and M St. will be completed
in the spring.
In spring 2010, the final
surface pavement for the entire
job will be applied. Once this
occurs, the striping for bike
lanes, permanent pavement
markings, and new traffic
signals will be installed. The
new bike racks and benches, as
well as final plantings are
scheduled for completion in the
spring.